Hi..

i have one finish material , which having five operation. Out of five third operation (Op.30) is external processing operation . Finish material use "metal rod "as a raw material.

After creation of production order system has cretaed PR for third operation.

Now I issued the" metal rod " for the first and second operation . After processing , third operation is External Processing,but my store person not getting the material in stock .Asi issued the metal rod for start the operation.

How should i deal with this condition.

What componenets i should maintain in routing of finish material.How store peson get the stock of material.

What is ideal case fro external process operation ??

Plasehelp out

Thnks

0 Likes
View Entire Topic
Former Member
0 Likes

Hi,

In Operation sub concentrating (Ext Op) , stock of components will not be getting increased.

if u want maintain the stock details of component , create inter material code between 2 nd & 3rd Operation.

After finishing the 2nd operation issue the material(from 2nd op) to sub contractor and receive the semi finished material for 3rd OP. Inthat case u have to follow material subcontracting cycle.

Pradeep