on ‎2008 Jul 28 9:09 AM
Hi..
i have one finish material , which having five operation. Out of five third operation (Op.30) is external processing operation . Finish material use "metal rod "as a raw material.
After creation of production order system has cretaed PR for third operation.
Now I issued the" metal rod " for the first and second operation . After processing , third operation is External Processing,but my store person not getting the material in stock .Asi issued the metal rod for start the operation.
How should i deal with this condition.
What componenets i should maintain in routing of finish material.How store peson get the stock of material.
What is ideal case fro external process operation ??
Plasehelp out
Thnks
Request clarification before answering.
Hi
Please check the control key of the work centers assigned for operation 2.
To get as stock control key - PP03 need to be maintained and for thrid operation which is externally processed control key should be PP02
Also ensure current components are allocated thru component allocation.
PP03 - Routing - in-house prod. auto. goods rct
PP02 - Routing/Ref. op. set - external proc.
Regards
Manikandan .J
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 30 | |
| 14 | |
| 9 | |
| 4 | |
| 4 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.