External Processing Operation

Former Member
0 Likes
2,153

Hi..

i have one finish material , which having five operation. Out of five third operation (Op.30) is external processing operation . Finish material use "metal rod "as a raw material.

After creation of production order system has cretaed PR for third operation.

Now I issued the" metal rod " for the first and second operation . After processing , third operation is External Processing,but my store person not getting the material in stock .Asi issued the metal rod for start the operation.

How should i deal with this condition.

What componenets i should maintain in routing of finish material.How store peson get the stock of material.

What is ideal case fro external process operation ??

Plasehelp out

Thnks

View Entire Topic
Former Member
0 Likes

Hi

Please check the control key of the work centers assigned for operation 2.

To get as stock control key - PP03 need to be maintained and for thrid operation which is externally processed control key should be PP02

Also ensure current components are allocated thru component allocation.

PP03 - Routing - in-house prod. auto. goods rct

PP02 - Routing/Ref. op. set - external proc.

Regards

Manikandan .J

Former Member
0 Likes

Thnaks for reply..

what will happened if i defined this key in operation. please explain

Former Member
0 Likes

please explain me again