on ‎2009 Aug 19 12:17 PM
Hello All
I am creating material cost estimate of FG whose components are SF & ROH-2. While creating cost estimate system gives an error message which states: :
*No cost element segment exists for 40103110 on 01.09.2009
Message no. CK048
Diagnosis
The consumption account found by automatic account determination for material STD-PRICE-SF does not exist for the date 01.09.2009 specified.
Procedure
Check the cost element segment's validity period
Check cost element
Or, if you have authorization, create a cost element which did not exist previously.
Create primary cost element*
Please provide your valuable inputs regarding this error message. Looking forward to your inputs & feedback.
Regards,
J K Tharwani
Request clarification before answering.
Dear Jitendar Kumar,
Goto T Code FSP0, and check the validity period for the account 40103110.
Check and revert back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 60 | |
| 30 | |
| 21 | |
| 11 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.