Hi experts,
Im junior sap ps cons. and ı have a question.
What are the differences between cj91 and cj01?
and what are the differences between cj2d and cj27 ?
Request clarification before answering.
Please review below, hope it will help to clear your query.
CJ01 for Operative WBS, Operative WBS against that we will create PR/Reservation and cost
CJ91 is used for Standard WBS which can be used as template
CJ2D is used for Structure Planning of Operative WBS
CJ27 is used for Project planning board : The project planning board has a central position in the Project System. It simplifies planning and controlling projects. The project planning board allows integrated processing of your project, giving you a graphic overview of the project objects. In the graphic interface you can create, edit and evaluate all the data for a project
for more detail refer link: https://answers.sap.com/questions/3024361/project-planning-board.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
One of the best starting points to learn about SAP is help.sap.com for PS use this link.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CJ06 for Project Definition and CJ01 for WBS
Under a project definition you can create multiple wbs elements with hierarchy for control and budget purposes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 22 | |
| 10 | |
| 9 | |
| 5 | |
| 5 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.