Sorry to Post the Same thread with the Same Subject line..I searched a lot in the forum,but i didnt get clue on my Requirment.
I have a scenario ,,where for single line item i need to do delivery for mulitple ship to parties...
In SO,Line itemwise ,i maintained 4 ship to parties...(Did some config in Partner determintaion,here i can able to add Ship to parties 4)
When iam doing the Delivery Delivery is not splitting based on this Multiple Ship to parties...
I activated in Delivery document ,the field Delivery split partner...
Its not Splitting the DC ......How can i split the Delivery
Thanks in Advance
Regards
raj.
Request clarification before answering.
Hi venky raj,
To do that you need to modify the copy routine between SO and Delivery, so when you have more than one Ship-to party for a single item line in the SO, then you create the same quantity of Deliveries as Ship-to party you have in the SO's item line.
Thanks in advance.
Mariano.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 30 | |
| 14 | |
| 9 | |
| 4 | |
| 4 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.