on ‎2010 Apr 21 9:47 AM
Dear Experts,
How Can I default the Progress version on the netwrok activity, instead of entering manually on each activity.
In IMG Define Measurement Method as Default Value, already maintained.
Thanking you.
Best Regards,
Abdul.
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Abdul,
Unfortunately, the version cannot be defaulted for activities. In the IMG step mentioned, you can customize a measurement method as default, but not the progress version.
Sorry for the inconvenience
Regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thank you for the reply.
1) Can we use the IMG settings Enter Measurement Methods for Order Type to achieve this?
2) Is it possible to default Progress Version for activities through substitution?
3) Is there any user exit / BADI, wich we can use to default Progress Version for activities?
Thanking you.
Best Regards,
Abdul.
Can we use the IMG settings Enter Measurement Methods for Order Type to achieve this?
This path is to maintain measurement methods for orders other than networks
Is it possible to default Progress Version for activities through substitution?
progress version field is not available in std field selection for substitution. however you may try using the exit in substitution
Hi,
I am able to default the measurement method when I am selecting the progress version by this settings, but where as when I am creating the activity the progress version is not getting defaulted which I need to enter manually.
Is it possible to default progress version also in the activity?
Tnx.
Abdul.
| User | Count |
|---|---|
| 58 | |
| 29 | |
| 21 | |
| 11 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.