Dear Experts,

How Can I default the Progress version on the netwrok activity, instead of entering manually on each activity.

In IMG Define Measurement Method as Default Value, already maintained.

Thanking you.

Best Regards,

Abdul.

View Entire Topic
Former Member
0 Likes

in IMG Define Measurement Method as Default Value, already maintained.

You will set default measurement method for a project object with respect to the progress version...so the default values will be taken only if you maintain that particular progress version...