on ‎2017 Feb 16 7:05 AM
Hi Experts,
We are having the problem in cost estimation.
In the BOM level 2017 we have added one new SKU (apple 19. Ml) valid from date 21.01.2017 in the BOM . which we are having the one exiting material (apple 23 ml) we have change BOM valid from date is 01.01.2017 to 21.01.2017.But old SKU ((apple 23 ml) has been linking with the Production versions. For old SKU they have done std cost estimate only KA status. I have delete the old SKU std cost estimation, PV's and mixed ratio as well.
If we are running std cost estimation for future old SKU has been updated in the cost rollup process. and new SKU (apple 19 Ml) does not appear in the cost rollup process.
PV valid start date is 01.01.2017 to 31.12.9999.
1701 PV valid date from 21.01.2017 new SKU

1701 PV valid before 21 date old SKU


BOM:

Why the new SKU is not pick up in the std cost estimation.For new SKU they don't want to mixed ratio.
Request clarification before answering.
HI Experts,
ANy one having any idea on the same..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We are not using any PV for new material. our question why the new SKU does not pick up the cost roll up process.
PV is don't locked same pv is using the other SKU in the production.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
and we are not using the new material for production version. our question why new material is not pick up in the cost rollup process
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I have checked new material we are not used any production version(in matserial master) and old SKU we have deleted the PV . Not sure why Still old SKU is picking in the cost estimation.
PV valid date: 01.01.2016 to 31.12.9999
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the validity for the new production version in the material master and lock the old version.
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Muktar,
If we are taking the qty structure date as below. For feature dates also We ran the cost estimation without saving mode, old SKU has been pick up in the cost estimation process not the new SKU.
Costing Date From 16.02.2017
Costing Date To 31.12.2017
Qty Structure Date 16.02.2017
Valuation Date 16.02.2017
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 46 | |
| 27 | |
| 17 | |
| 6 | |
| 3 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.