Hi, I am trying to perform whole of the consignment cycle. I have created a consignment PO, but the info record is not populating in the info record field in the PO. When I tried to go the GR by MIGO it didnt allow me to do the GR it gave the error " GR not possible for it". I created an inbound delivery and then did the GR. When i did the gr from the invbound delivery i have 2 entries under confirmation tab in the item details with 2 inbound deliveries. Now I can see the stock in the consignment stock but I am not able to do the transfer posting from consignment to my own stock and hence not able to do MRKO.

Please suggest where all I am going wrong. I am executing this cycle for the first time.

0 Likes
View Entire Topic
Former Member
0 Likes

In  Po  tab  , in  confirmations  tab what  you  maintained as  conf., control ?

Former Member
0 Likes

Inbound DI/Order Ack

Former Member
0 Likes

HI,

1. First Maintain Consignment PIR with Vendor, Material  & Prices with validity Period

2. Create Consignment PO,

3. Do in bound delivery

5. Do GRN (105)with Consignment PO or in bound delivery.

6. After GRN no accounting document will generated check it.

7. do Transfer Posting with 411K, check Material document with accounting document, Price is pick up PIR.

8. do MRKO with 411K Material document.

kunal_ingale
Active Contributor
0 Likes

Hi ,

the given Error is well discussed on the forum , Please search on net for more idea.

Points  to be checked ,

1) Goods receipt is ticked in PO delivery

2) Delivery completed not ticked in the delivery tab.

3) No confirmation key in the confirmation tab.

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/a065d4dc-1195-2e10-569b-f1e755b42...

Thanks

Kunal