Commitment values

Former Member
0 Likes
1,892

Hello Experts,

I am facing issue in commitment value. A matl component has been attached to an activity & a PR has been generated accordingly.

Suppose the value of it is 100,PO created, & 50% GR done against it.

Now, when  check the slr_558 report, it shows BDGT(200), ATUAL(50) , COMMITMENT(100) , ASSIGNED(150), AVAIL.(50).

I have reconstructed the DB by cjen,cjbn,rkan..,rkac..programs. etc., but still the issue persist.

The problem is even if complete complete GRN is done, then also the commitment values are seen as 100, instead of 0.

In OPSC, in ctrl indicator, Planning indicator is not ticked.

In OPSV, for 20(N/W), "appended plan update" & "Assign funds in Plan" indicators are ticked.

Kindly Suggest.

BR.

View Entire Topic
Former Member
0 Likes

Hi,

Can you please share the S_Alr_558 and CN41 report screen shots.

Regards,

Rao.

Former Member
0 Likes

Hello Rao,

KFA the imgs

  cn41

  slr

  cji5

313,57 is the original value from PR.which does not get deducted.

BR.

Former Member
0 Likes

Hi,

Please check below points,

1. Whether you have created the PO with reference to PR or not.

2. If yes, check the PR number which is given in PO as reference and PR No which is showing as commitment.

If possible pls share screen shots for the above points..

Regards,

Rao

Former Member
0 Likes

Hi ,

    Commitments are created from single PO created with reference to the PR only.

PR generated through PS.

BR.