Hello Experts,

I am facing issue in commitment value. A matl component has been attached to an activity & a PR has been generated accordingly.

Suppose the value of it is 100,PO created, & 50% GR done against it.

Now, when  check the slr_558 report, it shows BDGT(200), ATUAL(50) , COMMITMENT(100) , ASSIGNED(150), AVAIL.(50).

I have reconstructed the DB by cjen,cjbn,rkan..,rkac..programs. etc., but still the issue persist.

The problem is even if complete complete GRN is done, then also the commitment values are seen as 100, instead of 0.

In OPSC, in ctrl indicator, Planning indicator is not ticked.

In OPSV, for 20(N/W), "appended plan update" & "Assign funds in Plan" indicators are ticked.

Kindly Suggest.

BR.

View Entire Topic
MTerence
Active Contributor
0 Likes

Hi Supriya,

Check whether below note is relevant to your case.

1901892 - Incorrect commitment value for service items


This report has lot of inconsistency, can you check in CN41N ?


Regards

Terence

Former Member
0 Likes

Hello Maria,

Thanks for the reply.

Currently going through the SAP Note shared by you which again redirects to S.N.1491430 - Incorrect Commitments for Service Items .

I am facing issues with commitments generated thr' materials. Have to check it once.

Hope, this will help out.

Any suggestion is welcomed.

BR.

MTerence
Active Contributor
0 Likes

Hi Supriya,

Can you please check whether this program RKACOR04 resolves ?

Regards

Terence

Former Member
0 Likes

Dear Maria,

  

As said earlier, all programs & tcodes have been executed for database reconstruction, but in vain.

I had run the report which messaged "No error record was found for selection"