on 2015 Jul 03 6:35 AM
Hello Experts,
I am facing issue in commitment value. A matl component has been attached to an activity & a PR has been generated accordingly.
Suppose the value of it is 100,PO created, & 50% GR done against it.
Now, when check the slr_558 report, it shows BDGT(200), ATUAL(50) , COMMITMENT(100) , ASSIGNED(150), AVAIL.(50).
I have reconstructed the DB by cjen,cjbn,rkan..,rkac..programs. etc., but still the issue persist.
The problem is even if complete complete GRN is done, then also the commitment values are seen as 100, instead of 0.
In OPSC, in ctrl indicator, Planning indicator is not ticked.
In OPSV, for 20(N/W), "appended plan update" & "Assign funds in Plan" indicators are ticked.
Kindly Suggest.
BR.
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Suresh,
I am not convinced with first two points mentioned by you. reason being whwther it is an ivstmnt or any other profile or even about budget tolerence limits, system is behaving rightly.
request you to make me understand the difference btw OKKP screenshots,
The issue is not that commitments not raised, they are. but they are not reduced by the amount the actuals are booked for the same.
BR
| User | Count |
|---|---|
| 57 | |
| 29 | |
| 21 | |
| 11 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.