on ‎2008 Dec 06 5:17 PM
Hi SAP gurus
I want to close the Project while closing i am getting error that purchase requisition commitment exists for the WBS . PR's created from the project builder and these purchase requistion are unwanted.
Tried by deleting the components / locking the WBS but still unable to close the project.
Need solution without doing any customization.
kindly give suggestions for this query.
Thanks
PP
Request clarification before answering.
If the commitment is due to PR, set the deletation flg. to PR & close the project. if you are getting any other message while closing check report CJI5 for any other commitament open for that project.
Regards
Nitin
Edited by: Nitin Patoliya on Dec 7, 2008 11:12 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 29 | |
| 14 | |
| 7 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.