Hi SAP gurus

I want to close the Project while closing i am getting error that purchase requisition commitment exists for the WBS . PR's created from the project builder and these purchase requistion are unwanted.

Tried by deleting the components / locking the WBS but still unable to close the project.

Need solution without doing any customization.

kindly give suggestions for this query.

Thanks

PP

View Entire Topic
nitin_patoliya
Active Contributor
0 Likes

If the commitment is due to PR, set the deletation flg. to PR & close the project. if you are getting any other message while closing check report CJI5 for any other commitament open for that project.

Regards

Nitin