Commitment date in process order has partial quantity does it impact unrestricted stock

former_member584050
Participant
0 Likes
1,214

Dear Experts,

In MMBE we have unrestricted stock of 18600 but sales order getting confirmed for only 560 we have
checked relevant master data and config settings from SD .

This stock came from process order in the process order in the commitment field we havce seen 560 quantity
instead of 18600 sales order getting confirmed for this 560 only which is being shown as committed quantity in the
process order.

Could you please suggest how this committed quantity impacting unrestricted stock availability.

View Entire Topic
rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Committed quantity in production or process order depended upon the component material availability.

If all components are available according to the ATP check components then you will have full committed quantity for order.

I don't think the process order committed quantity has to do anything with sale order confirmation.

First check the CO09 for the Material and Plant with Checking Rule A what is cumulative quantity available.

Unrestricted stock of 18600 but sales order getting confirmed for only 560

Also check if sale order is in make to stock (Unrestricted stock) segment. If it in MTO segment then check process order availability date and quantity.

Best Regards,