Hi everyone!

I'd like to know about Batch Split:

- Can i allow batch split in a sales order or in a delivery just clicking a flag or sometinhg like that?

- Where can i manage batch split? i mean allowing it or not depending on my needs

Regards.

Eduardo

View Entire Topic
Former Member
0 Likes

Hi,

a material is managed in batches, you can carry out a batch split for every component.

This means that if you split a batch, you assign more than one batch to one component. In this case, each batch is displayed as a separate component in the component overview.

Batch splits can only be triggered manually in the production order.

Prerequisites

The following requirements must be met for batch splitting:

The material master record of the material must specify that the material is managed in batches.

Batches must exist for the material.

Branch to the component overview screen.

To carry out automatic batch splitting via batch determination, proceed as follows:

Select the component that you wish to split and choose Component - Batch management - Trigger batch det.

The system lists all batches that meet the selection criteria and that have available stock on the requirements date.

Distribute the required quantity as required over the existing batches.

Select copy.

The system copies each batch as a separate component into the component overview screen.

To carry out manual batch splitting with manual batch assignment, proceed as follows:

Select the component for which you want to carry out batch splitting. Choose Edit - Insert - Batch split.

Enter the batch number and the required quantity manually in the component.

Save your entry.

regards,

Siddharth.