I would like to schedule production orders by changing schedule dates. But in the same, I would like that basic dates are not changed (especially end basic date) and would like to keep original values.

The setting 'do not adjust basic dates' simply does not work in this way. Did anyone achieve that?

To be honest I think its even a bug in the system that when you go to order>scheduling you can not save the scheduling settings (adjust/not adjust). When you enter production order again it comes back to original settings from order type and your changes are gone.

Thx.

View Entire Topic
lingaiahvanam
SAP Champion
SAP Champion
0 Likes

Hi,

As mentioned by Brahmankar check and test the scenario.

Additionally the following SAP note to help to understand the scheduling of production orders.

https://launchpad.support.sap.com/#/notes/150007

Best Regards,

Lingaiah