I 'm using MM01 to create purchasing view, after that, when we create PO, but it says "

Material not maintained by Purchasing

Message no. ME046

so in MM side, is there any transaction code we need to execute to confirm the change? thanks

0 Likes
View Entire Topic
Prasoon
Active Contributor
0 Likes

Hi,

   Pass the material and plant to MARC table and check whether E is there in maintenance status or check the purchasing view details hav been updated there. If its there, system wont thorw any message while creating PO for the material and plant.

Hope its helpful.

Regards,

AKPT