Application Development and Automation Discussions
Join the discussions or start your own on all things application development, including tools and APIs, programming models, and keeping your skills sharp.
cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Scheduling margin key?

Former Member
0 Likes
1,855

Hello All,

I was trying to create a material in a plant and I get an error 'Enter the scheduling margin key'. Could anyont help me on this? This is really urgent Please.....

Thanks in advance,

Anju

2 REPLIES 2
Read only

Former Member
0 Likes
617

Try this out...

You define the order float in the scheduling margin key, The scheduling margin key is copied from the material master. The float before production or float after production and the release period are defined in the scheduling margin key

For Customizing for Shop Floor Control, by choosing Operations --> Scheduling --> Define Scheduling Margin Key .

The scheduling margin key is assigned to the material ( MRP area in the material master) and is transferred when the production order is created. These values can be changed in the production order.

Regards,

Bhumika

Read only

Former Member
0 Likes
617

k