Hi all,

we are upgrading to ECC 6.0 from 4.6c. As part of this project, I need to make some changes in sheduled jobs. How I can change them?

Are they going to run in new system without problum if client number is same?

Do I need to make any changes?

Thanks

Shiva.

Hi all,

we are upgrading to ECC 6.0 from 4.6c. As part of this project, I need to make some changes in sheduled jobs. How I can change them?

Are they going to run in new system without problum if client number is same?

Do I need to make any changes?

Thanks

Shiva.

1 REPLY 1
Read only

former_member194669
Active Contributor
0 Likes
303

Hi,

For changing the jobs

To change the schduled timings of particular job,

1. goto SM36

2. Give job name

3. Select start condition

4. Select date&time

5. Give period Values button bottom-side of the pop-up

6.Select the relavent period values and save it and again save it

But after upgrade if any changes in the variants, then scheduled jobs have to be rescheduled and also variants have to be recreated.