2009 Jun 30 2:56 AM
Guru,
Enter the Transaction code - GP12n in user pc the following error message display...
"Planner profile SAPFMPL contains no tasks for table V_GLFLEXT".
For testing purpose i give full access like SAP_ALL at that time also the same error message.
Pls advice how to rectify this...
Regards
Rajesh.
2009 Jun 30 6:13 AM
Hi,
This is evident that it is not an authorization issue. Even testing was not required with SAP ALL. Most of the cases where there is an authorization issue we will find an error message pointing to the authorization missing statement. Please contact the functional team who deals with this table or View V_GLFLEXT and ask to populate the table. Also mention them clearly that this is not an authorization issue.
Regards
Aveek.
2009 Jun 30 6:13 AM
Hi,
This is evident that it is not an authorization issue. Even testing was not required with SAP ALL. Most of the cases where there is an authorization issue we will find an error message pointing to the authorization missing statement. Please contact the functional team who deals with this table or View V_GLFLEXT and ask to populate the table. Also mention them clearly that this is not an authorization issue.
Regards
Aveek.
2009 Jun 30 6:28 AM
Aveek,
Exactly, Problem solved. It is not authorisation problem some customize table default values problem.
Thanks
Rajesh.
2009 Jul 30 9:22 AM
can you explain me the steps which we need to fallow in Project i am also having the same probles
thankls in advance