‎2009 Mar 12 1:59 PM
Hi Experts,
We are facing some peculiar issue with QPR2 transaction.Please help us in resolving the issue,
QPR2 -- Changing sample
User can able to change the physical sample of other plants , even though he was given access to only one plant.
In SU24, Q_Material and Q_Tcode authorization objects are having check Indicator status as "Check".
We have Switched on the trace for the user,and in the report surprisingly the auth object Q_Material is not getting checked ( which includes WERKS (Plant) as field).
Your inputs are really appreciated,
Thanking you in anticipation,
Patron.
‎2009 Mar 12 2:04 PM
‎2009 Mar 12 2:11 PM
> We have Switched on the trace for the user,and in the report surprisingly the auth object Q_Material is not getting checked ( which includes WERKS (Plant) as field).
In that case I suspect the authority check is not present in the program code. If it were, and in SU24 was set to 'do not check' it would still appear in the trace as far as I know.
‎2009 Mar 16 5:17 PM
Hi,
Please reques the ABAP team to see what are the authorization checks defined in the calling programs by the transaction and modify the porgrams as necessary. Or esse you can raise a request with your client to create custom transaction defining the authorization checks for required object.
Regards,
Gowrinadh
‎2009 Mar 12 2:14 PM
Hi Friends,
We are using ECC 6.0.
Check indicator for Q_material is "Check".
Thanks
Patron.