‎2007 May 04 3:29 PM
Hi friends,
I have implemented a oss note, as per the instructions given to me, but in that
after implementing the oss note using transaction SNOTE, i am getting implimentation status as 'completed' and processing status is 'in process'.
Then how can i know that my oss notes is completed or what is the test conditions for this oss notes.
with regards,
sharma.
‎2007 May 04 3:36 PM
Hello Sharma,
You have to consider the status of the note: completed means that the note has been implemented.
Then you can classify this note after testing your program and everything works fine, ie the error has been corrected.
That's why it is "in process".
Regards,
Walter
please reward points for good answers
‎2007 May 04 3:36 PM
Hello Sharma,
You have to consider the status of the note: completed means that the note has been implemented.
Then you can classify this note after testing your program and everything works fine, ie the error has been corrected.
That's why it is "in process".
Regards,
Walter
please reward points for good answers
‎2007 May 04 3:43 PM
Hi walter,
Thanks a lot, I think u know my oss notes scenario. Then my main doubt is
how to test this oss notes. What do you mean my processing status is ' in processing'.
regards,
sharma.
‎2007 May 04 3:50 PM
If possible, check the correction mentioned in the snote are implemented in your system or not. If it is implemented then there is no problem in Snote implementation.
‎2007 May 07 7:52 AM
Symptom of the note:
Your system contains old deliveries that are closed from a business
perspective, but characterized as open by the system for a number of
different reasons. This has consequences for data archiving:
o Open deliveries cannot be archived because the overall processing
status "Completed" is an absolute requirement for deliveries to
be archived (see Note 138666).
o Open deliveries also affect whether or not sales orders can be
archived because these orders can only be archived once they are
completed as subsequent documents for related deliveries. Just
one open delivery in the document flow can prevent archiving of a
scheduling agreement covering a large number of subsequent
deliveries.
You should check if it is still the case after the note implementation.
Regards,