Hello
I created 5 transports in dev and moved all 5 to Q for testing. All 5 of them are changes for the same program. Now should I just move the latest transport to prod or should I move all 5 in the same order? Thanks.
Jack
‎2009 Aug 14 4:51 AM
Hi Jack ,
It depends on what were the content of the TR. if they was just the program , then you can import the final transport only.
So please check the content of all the TR's , if it just contain the report then you can import the final transport else the recommended way will be to import all the TR in the correct sequence.
Regards,
Arun
‎2009 Aug 14 12:42 AM
Try this
SE01--> create a new transport ( with no object inside )
then
SE01> Enter the new transport created and press display> select the transport using single click in the parent --> and choose "include objects" (CTRL + F11) > system will popup for transports need to transported> and choose list from multiple requests--> give all your 5 transports here > system will imports all objects from the transports given> then right click on the parent transport --> and choose "sort compress" then transport the new transport request.
Thenyou don't need to all 5 old transports to PRD. All the objects from 5 previous transports will imported into new transport
a®
‎2009 Aug 14 4:18 AM
It would be better u delete all the 5 request and create a single request and transport to Q and then
to production, which can reduce this kind of confusion.
‎2009 Aug 14 4:51 AM
Hi Jack ,
It depends on what were the content of the TR. if they was just the program , then you can import the final transport only.
So please check the content of all the TR's , if it just contain the report then you can import the final transport else the recommended way will be to import all the TR in the correct sequence.
Regards,