hi
can anybody tell what is the meaning of MRP Controller in the table MARC
regards
kq
‎2007 Nov 02 2:10 PM
Hi,
The following link will give some overview related to MRP controller.
http://www.sap-img.com/pp017.htm
But i don't have info related to MARC linkage.
a®
‎2007 Nov 02 2:14 PM
Good..
Material Requirement Plan Controller more often we call Expaditors.
Usally in any plant group of materials (Either finished goods or raw materials) will be allocated to one MRP controller....
‎2007 Nov 02 2:20 PM
Hello,
When you create an Material and choose the MRP views, MRP controller is basically an group or an individual person responsible for the planning of that material.
In other words, the person responsible for a group of materials in MRP in a plant or company.
Material that takes part in material requirements planning must be assigned to an MRP controller.
In MARC, DISPO is a 3 char and you can go to T024D to get all the MRP controller + the name of the group or the person.
Thanks,
Suresh Ganti