2011 Nov 23 11:50 AM
Hi experts,
I have a lsmw that loads a file into om infotypes.
the lsmw is a succession of screens: for each line in the file, there is a creation of 2 occurences .
I want to skip the creation of the second occurence depending on the value of a field.
Is it possible?
Thkx in advance.
Obviously you are using a recording. Recordings always have fixed screen sequence, you cannot dynamically change it based on field contents.
Possible workarounds:
- try creating a recording that contains all potentially relevant screens for all scenarios
- create separate recordings for each scenario, and process only the respective portion of the source data with each recording.
Thomas
P.S. please use more meaningful titles when posting
2011 Nov 23 12:03 PM
Obviously you are using a recording. Recordings always have fixed screen sequence, you cannot dynamically change it based on field contents.
Possible workarounds:
- try creating a recording that contains all potentially relevant screens for all scenarios
- create separate recordings for each scenario, and process only the respective portion of the source data with each recording.
Thomas
P.S. please use more meaningful titles when posting