hi abapers i would like to know wat is meant by one complete life cycle??

1 ACCEPTED SOLUTION
Read only

Former Member
0 Likes
612

high level design of the upgrade life cycle.

Activity

Description

SPDD adjustments (Adjustments in Data Dictionary objects)

Adjustment of data dictionary objects

Identify SPAU objects and Custom objects

Prepare the list of SPAU objects and Custom objects

Reassessment of effort for modification and adjustment activity

Reassessment of effort required for modification and adjustment activity

Object Tracking Sheet

Prepare the object tracking sheet

Modification and adjustments of

SPAU and Custom objects

Modification and adjustment activity

Object Testing (typically for custom objects)

Primary testing of object to avoid any short dump

QA Objects and documents

Quality Control of modification and adjustment

Release Request

Transport the request from DEV to QA system

Delivery of Objects to Client

Completed objects are delivered to the client

Integration Testing

Integration testing

Rework Objects

Objects requiring rework after integration testing by the client and receipt of feedback

Acceptance

Acceptance from client

<REMOVED BY MODERATOR>

Edited by: Alvaro Tejada Galindo on Feb 5, 2008 10:52 AM

high level design of the upgrade life cycle.

Activity

Description

SPDD adjustments (Adjustments in Data Dictionary objects)

Adjustment of data dictionary objects

Identify SPAU objects and Custom objects

Prepare the list of SPAU objects and Custom objects

Reassessment of effort for modification and adjustment activity

Reassessment of effort required for modification and adjustment activity

Object Tracking Sheet

Prepare the object tracking sheet

Modification and adjustments of

SPAU and Custom objects

Modification and adjustment activity

Object Testing (typically for custom objects)

Primary testing of object to avoid any short dump

QA Objects and documents

Quality Control of modification and adjustment

Release Request

Transport the request from DEV to QA system

Delivery of Objects to Client

Completed objects are delivered to the client

Integration Testing

Integration testing

Rework Objects

Objects requiring rework after integration testing by the client and receipt of feedback

Acceptance

Acceptance from client

<REMOVED BY MODERATOR>

Edited by: Alvaro Tejada Galindo on Feb 5, 2008 10:52 AM

3 REPLIES 3
Read only

Former Member
0 Likes
612

ASAP Methodology: The SAP Project Development Life Cycle.

Project Preparation:

The first step in ASAP is Project Preparation. In this step the Functional Consultant will analyse the business process and define the system for SAP and will give the time line for the project. The Manpower required and the budgets are also considered in this step.

Blue Print Preparation:

This is second step in ASAP Methodology. In this step the Project Preparation scenarios are finalised. A out line of the Project is given in this step.

Realisation:

In this step actual development is taken place. The ABAPer is responsible for this step.

Testing:

In this step the development done by the abaper is being tested. This is the area where the Unit Test Document is prepared (i.e. Positive Testing and Negative Testing).

GO live and Support:

This is the final stage where the project is running in the live environment. In this step the bugs if any that are found in the go live procedure are fixed and the project will be considered as support project.

<REMOVED BY MODERATOR>

Edited by: Alvaro Tejada Galindo on Feb 5, 2008 10:51 AM

Read only

0 Likes
612

fine prakesh thanku for ur inf.. will every company follow only ASAP metholodigies r is there any more metholodigies under sap product development

Read only

Former Member
0 Likes
613

high level design of the upgrade life cycle.

Activity

Description

SPDD adjustments (Adjustments in Data Dictionary objects)

Adjustment of data dictionary objects

Identify SPAU objects and Custom objects

Prepare the list of SPAU objects and Custom objects

Reassessment of effort for modification and adjustment activity

Reassessment of effort required for modification and adjustment activity

Object Tracking Sheet

Prepare the object tracking sheet

Modification and adjustments of

SPAU and Custom objects

Modification and adjustment activity

Object Testing (typically for custom objects)

Primary testing of object to avoid any short dump

QA Objects and documents

Quality Control of modification and adjustment

Release Request

Transport the request from DEV to QA system

Delivery of Objects to Client

Completed objects are delivered to the client

Integration Testing

Integration testing

Rework Objects

Objects requiring rework after integration testing by the client and receipt of feedback

Acceptance

Acceptance from client