2007 Feb 15 10:11 AM
hi
i developed a report , in saved in package and have one request number,
inext time i developed another report and saved in same package .
but it saves under same package , and under same request number.
i want this report saved under same package but different request number.
2007 Feb 15 10:14 AM
At the time of saving the new report, the system will ask for a request no. Specify a different request number in the pop-up that appears, The report will be saved in that request.
Manoj
At the time of saving the new report, the system will ask for a request no. Specify a different request number in the pop-up that appears, The report will be saved in that request.
Manoj
2007 Feb 15 10:14 AM
At the time of saving the new report, the system will ask for a request no. Specify a different request number in the pop-up that appears, The report will be saved in that request.
Manoj
2007 Feb 15 10:17 AM
Hi,
On saving teh second request you will get a Pop Up with the option Create Request , Own Request. Select the Create request option so that a new transport request is created for your report.
Regards,
Sowmya
2007 Feb 15 10:18 AM
in the screen presenting the TR number there will be a button as create .
give the package u want to store and enter.
click that and it will allot a new Tr in the same package .
regards,
vijay
2007 Feb 15 10:18 AM
Hi,
wen saving the program, a pop up will appear with asking the request number, if you dont want the program to be stored in the request number displayed, then u have two options you can create one more request and save it there or enter the request number where u want it to be stored
thanks
2007 Feb 15 10:20 AM
HI,
When u will save Report in the same package,there will be option own request or create new.By choosing new request you can save ur Report in another request in the same package.
Regards
Gaurav
2007 Feb 15 10:46 AM
assign the package name and press enter it will show the request no press F8 here and give any text press enter it will assign to the new request no.
regards
shiba dutta
2007 Feb 15 10:49 AM
Hi
At the time of saving the new report, the system will ask for a request no. Specify a different request number in the pop-up that appears, The report will be saved in that request but specify the same Package(Development class). So that 2 programs now saved in the same Package but in diffrent Request numbers.
Regards,
kumar
2007 Feb 15 10:56 AM
Hi,
as it looks like the second Report is already assigned to the same Request as the first, you need to delete it from this Request.
Call Transaction SE10, select your Request, go into Change-mode and delete the Program from your Object list.
The next time you change the second report, the system will ask you for a Request. Now you can select or create a new one.