I am wondering how to schedule the activity of testing a manual control offline, I mean using AIF. Could you please help?
Thanks,
Kind regards,
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hello John,
You will need to activate them through SPRO.
You should tick the checkbox in the SPRO customizing “Configure OWP Business Scenario”. There you can select what category you want to send the offline test. Afterwards, schedule a normal test and it will go to the user with a PDF attached.
Regards,
Fernando