In SAP Cloud ALM, we've been incrementally adding features to our APIs. We've reached a critical mass, allowing you to powerfully automate implementation projects and create new added value.
To help you get started, we recently published a Jupyter n...
This week, on February 15, 2022, we added a feature to SAP Cloud ALM which we have been waiting for a long time: integration of Requirements and Test Cases.
You can now assign test cases to requirements - bi-directionally
Assigning a Test Case to...
Today, to celebrate the Year of the Tiger, we published the latest updates to the SAP Cloud ALM APIs in the SAP API Business Hub. The updates are primarily in the Tasks API but there are also new features in the Projects API.
Er... just kidding abou...
Today, January 26, 2022, is SAP Cloud ALM feature delivery day. I posted previously summarizing these new features. Here, I want to post in some detail about a nice new personalization feature: marking items in the Tasks and Requirements lists as fav...
As we do every second week, the SAP Cloud ALM team has released a number of new features today (Wednesday, January 26 2022). I'll give a brief outline of the new features for the Projects, Tasks, and Requirements apps here.
Important! You May Now on...
Here's an example. The start date of this task is linked to the predecessor. The duration is manually set to 4 days. The completion date is calculated based on Start Date + Duration. When I update the completion date of the predecessor, the system wi...
Have you maintained the durations of the tasks?The system needs to know this in order to calculate the start or planned completion date.For example, if you link the start date of a task to its predecessor, clear the planned completion date, and enter...
Hi Giovanny,
You are right. Approved requirements may not be deleted. This is a restriction we have in order to preserve the record of requirements.
If this is an issue, or you feel that we should change this, you can always submit a request to SAP...