I recently test functionality in my system - Create consistent master data for preventive maintenance. It is worked as describe in SCN blog - Create consistenet preventive plan. Note # 2539196
But i am not clear about purpose of “Do no...
Dear All,In IH01- if field system status choose for equipment, response time increase.Whether it is general problem in IH01 or not.Any solution available for reduced respose time for IH01?Best regards,Santosh
Hi Expert,During Breakdown maint. scenario ,Time confirmation work start time & date copy from malfunction notification.Aftr final confirmation final time & date copy in notification.Thanks,Santosh
Hi expert,During time confirmation work start date copy from malfunction notification & entering end time in confirmation should copy into malfunction notification.Tahnks,Santosh
Hi Expert,I have define diffrent order types to two plant, but PR document type are same for both plant bcoz it assign at maitnt.order category.I want to assign diffrent PR document type to respective plant for orders.Regards,Santosh
Dear Rakesh, You can use seprate G/L for procurment of material. It can be done with customizing default value profile for procurment in setting of order type. For stock material automatic G/L determination when reservatin created from PM order. With...
Dear Jerry, SAP provided diffrent improvement one of it is diffrent log text copy option in PM order purchasing tab for non stock material or services. Long text copy from PM order to purch. requistion as per your define rule. Please refer below link...
Hi Hemant,Functionality is very much useful for maint planning. I recently test this functionality in my system. It is worked as you describe above.But i am not clear about purpose of “Do not allow” option. My guess is that after click on this option...