Hi Serge,
What would be the result if you used the Planning Board, with "Bottom-up" scheduling and activities strictly defined the WBS dates(i.e. shorten the WBS dates if that is the case)?
Another point to be raised here is midway through 2023, cu...
Another option is to use Microsoft Project or P6 and integrate with PS networks and work orders. As SAP's integration tool is not supported anymore, there is a SAP certified BTP based integration option now called Carbon by Rizing.
Hello,I don't think it is necessary to create the project automatically as ling as the manual assignment is done correctly. Did you assign the task to the employee who is going to time write to it?Regards,Mustafa