on ‎2014 Sep 15 9:56 AM
Hi All,
Recently we have done QA refresh & copied with production data.
For 0vendor master data we are extracting data from ECC source system. When I was trying to execute the DTP it is pointing older source system. We tried to create new DTP but when I'm executing still it is showing older system.
By using RSBKDTP_BDLS program I forcefully tried to convert old source system to new source system but we are unable to solve this issue.
Here I'm attaching the issue .Please help on this issue.
Best Regards,
Sammar.K
Request clarification before answering.
Hi,
Assuming as your facing this problem at BWQ.
So at BWQ please check table - RSLOGSYSMAP,
above table need to have the entries of ECC quality server as source and BW Quality server name as target system.
if not then ask basis team and maintain it.
later you can run your dtp.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 7 | |
| 6 | |
| 6 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.