Hi to all,
some of my customers, asking for me, to dismiss Businness Object, in despite of the fact that they want to use Analysis for office to make their workbook reports.
They have got BW 7.5. There is some way or some work around to schedule the workbooks without the BO machine;
I noticed, for exemple, that it is possible to save a workbook AfO in a repository BW instead of a repository BO: it is possible to schedule this kind of woorkbook using the BEx Broadcasting?
Kind regards
Rino Scia
Request clarification before answering.
Gennaro - I don't think things have changed from here: https://archive.sap.com/discussions/thread/3718935
My guess - since SAP said they are not investing in BW 7.5 (they are investing in BW/4HANA) I wouldn't expect this to change or work - this is my opinion only
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.