cancel
Showing results for 
Search instead for 
Did you mean: 

Variance

01-12-2009 8:06 AM
1402 views 3 comments Go to solution
0 Likes
SAP Managed Tags
Subscribe

Hi,

Can anyone explain me about variance w r t Product costing?

Thanks and Regds

Sridhara K N

0 Likes

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Likes

Dear

The difference between planned cost and actual cost is called variance.

Steps to be followed

1. After Final Confirmation of Order (Status: CNF) make GR for order using T.code: MIGO / MB31 so Production Order Status will be DLV.

2. Then complete the order technically by using T.code: CO02--> Functions (Menu)---> Restrict Processing -


> Technically Complete. You can carry out TECO for multiple Orders in T.code: COHV (Mass Processing).

3. Now Calculate Overheads using T.code: KGI2 - Individual Processing

CO43 - Collective Processing

4.Calculate WIP using T.code: KKAX - Individual Processing

KKAO - Collective Processing

5.Calculate Variance by using T.code: KKS2 - Individual Processing

KKS1 - Collective Processing

6.Finally do the settlement of Order in T.code: KO88 - Individual Processing

CO88 - Collective Processing

Answers (2)

Answers (2)

Former Member
0 Likes

Hi,

Variance Analysis

Use

You can use product drilldown to display the existing variances between planned and actual costs, or target and actual costs (see also : Terminology in Product Cost Controlling)

Variances are the difference between planned and actual costs.

Planned values are adjusted to a reference base, as a rule to the actual values, in order to calculate variances between target and actual costs. This adjustment is performed during variance calculation. You calculate variances in period-end closing of Product Cost by Period or Product Cost by Order. During variance calculation, the variances to be analyzed are distributed to individual variance categories. These variance categories can be displayed in the information system.

If variances have not yet been calculated, target costs can be calculated dynamically in the information system. The target costs are calculated on the basis of a target cost version.

Prerequisites

Before you use the reports Target/Actual/Production Variances and Variance Categories, you must have already performed variance calculation in period-end closing of Product Cost by Order or Product Cost by Period.

1. _Target / Actual / Production Variances_

Use

Report with which you can analyze the results of Variance Calculation in the following application components of Product Cost Controlling using product drilldown:

  • Product Cost by Period

  • Product Cost by Order

The reporting time frame can be cumulative or limited.

This report shows the results of variance calculation. The results are dependent on which target version was specified at report call.

You can call up a detailed report for the variance categories to investigate the production variances in more detail. There are two scenarios for the interpretation of the data:

Scenario 1: Standard costs, alternative material cost estimate, preliminary order cost estimate versus (if necessary, net) actual costs

Scenario 2: Standard cost estimate for the material versus planned costs for the order

Standard cost estimate for the material versus planned costs for the order corresponds to target cost version 2 (planning variance)

2. Target / Actual Comparison

Use

Use for product drilldowns:

Report with which you can analyze the target and actual data in the following application components of Product Cost Controlling using product drilldown:

*Product Cost by Period

*Product Cost by Order

The reporting time frame can be cumulative or limited.

This report is used to compare the target and actual data that was determined during Variance Calculation. The results of variance calculation are based on the target cost versions specified for the report: Different variances are considered, depending on the target cost version

Features

Data Displayed

The following data is shown based on key figures and/or original cost elements:

*Target costs

*Actual costs

*Target costs per unit

*Actual costs per unit

*Absolute variances = Actual costs u2013 Target costs

*Percentage variances = Absolute variances / Target costs

The variances can also be displayed per unit.

The above figures are based on the costs per unit of output.

*Target quantity

*Confirmed quantity

*Absolute variances = Target quantity u2013 Confirmed quantity

*Percentage variances = Absolute variances / Confirmed quantity

3. Variance Categories

Use

Report that you can use with product drilldown to analyze the individual variance categories for the following application components:

*Product Cost by Order

*Product Cost by Period

The reporting time frame can be cumulative or limited.

This report makes it possible for you to analyze the results of the variance calculation. The results of variance calculation are different depending on the target cost version specified for the report.

You can compare the following costs:

*Target costs that have been calculated on the basis of standard costs against actual costs (without work in process and scrap variances).

*Target costs that have been calculated on the basis of a preliminary cost estimate of an order (product cost collector or manufacturing order) against actual costs (without work in process and scrap variances).

*Target costs that have been calculated on the basis of an alternative material cost estimate (for example, modified standard cost estimate, current cost estimate) against net actual costs (without work in process and scrap variances).

*Target costs calculated on the basis of standard costs against planned costs of manufacturing orders.

Structure

Data Displayed

The following variance categories are shown based on key figures and/or original cost elements:

*Scrap variance

*Input price variance

*Input quantity variance

*Resource-usage variance

*Remaining input variance

*Mixed price variance

*Output price variance

*Lot size variance

*Remaining variance

Thanks,

Vinodh

Former Member
0 Likes

Hi,

When you run the Std cost estimate system will provide the Planned Cost for a material based on the Quantity Structure maintain.

Whereas as you produce a product you may have the actual cost ( based on the components consumed and actual activity timings used for the production of the product) The difference between the Planned cost and Acutal Cost is termed as Variance.

regards

radhak mk