Hi Experts,
I need to develop reporting on commitment, budget and actual values.
Do you know in which tables these values are stored ?
Thanks and Best Regards, Manuel
Request clarification before answering.
RPSCO
COEP: Actual Costs
COOI: Commitment
COEJ: Planned cost
BPGE: Budget overall
BPJA: Budget annual
Also have a look at standard PS reports in tcode CJE0.