I want to develop report as Monthly work Progress report for Construction Company.
In this Cumulative amounts are involved in terms of planned, actual , future.
whether i can get some standard reports for reference or please suggest me the overall path/steps i should follow.
Request clarification before answering.
Dear Experts,
we deal with development projects, Unit rate contract.
Scenario is like some of the construction activities are in house and some are subcontracting.
Now the top management needs a report which give monthly progress overview
in terms of costs planned, actual and forecast(cumulative).
As this is my first report to be developed,(already discussed with our ABAPer)
please give the guidelines in which direction i should apply logic and how.
or please suggest any link regarding this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try writing the Report Painter report (grr1) and use Cost elements to get the planned/actual figures.Then you may add the "in period" values ( using formulas in the report design) in order to get the cummulative values.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
construction company handles both unit rate contract and lump sum contract, which scenario you are looking for.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try using Report Writer/ Report painter. Discuss with your ABAP guys. They will help you on this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 13 | |
| 7 | |
| 7 | |
| 5 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.