Release projects automatically

08-19-2009 1:13 PM
1592 views 8 comments Go to solution
0 Likes
SAP Managed Tags
Subscribe

Hi experts.

I will like to release projects when they reach a user status which i have created previously.

I explain when i create a project, it has to be approved by a project manager, then by a project leader, and then by a sales leader.

What i want is , when it reaches to the last status Checked Sales Leader i wolud like that the project releases automatically. Nowadays we are opening the project and releasing it manually.

I would like to know if it can be done without using workflows, (if we have to use it we will do, but we want to know if is possible to avoid it).

In the customizing i have found the transaction ok02 but in there it works wrong, because it changes to the status when we release it.

Thanks for helping.

0 Likes

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Likes

Dear,

or you can use the milestone function also to release the WBS/Activities .

Regards.

Former Member
0 Likes

This could be useful, but i would like to release the whle project.

Anyway can you explain me how to do it?

Thanks.

Alex

Former Member
0 Likes

Dear,

You can assign the milestone to activity and go the milestone function tab and then tick the function and tick release following activity and select the s/s status.

http://help.sap.com//saphelp_erp60_sp/helpdata//EN/e7/b3851ed30711d2a6ae0000e82de7c3/frameset.htm

link is there for your help.

Sukhveer.

Former Member
0 Likes

Thanks a lot, but it doesn´t help me because what i need is to release the whole porject, including the header, and the milestone, i mean the reference to release it is when the user status of the header reaches to the last status, and it reaches to the last status during the workflow.

Thanks a lot for your help, but i am afraid i will have to use a workflow.

Thanks

Alex

Answers (2)

Answers (2)

Former Member
0 Likes

Using OK02, for that user status where you want auto-RELE,

double-click to display all business transaction, for Release business transaction, check the radio button under Set Column.

Edited by: Feng Hwa Hui on Aug 20, 2009 6:45 AM

Former Member
0 Likes

I knew it, but it works just the opposite, when you release the project, it goes directly to the status that you flag in ok02.

Thanks for your help.

Former Member
0 Likes

This message was moderated.

Former Member
0 Likes

Yes i knew it was possible by using a workflow, but i needed to know if there was another way.

Thanks a lot for your help.