Hi All,
I have created WBS BOM for xxx WBS Element
when i do MRP Run against that WBS Element, only Planned order gets created for finished material, But PR not generated for WBS BOM components (won't display in MD4C)
and after planned order to Production order creation
in Production Order, when i do Read PP Master data then only WBS BOM get copied in Production Order & after MRP run on same WBS PR will generate & display in MD4C result.
why Read PP master data is mandatory in case of WBS BOM
Please Suggest
Request clarification before answering.
Hi Pushkar,
If for the WBS BOM components in MRP4 View ind/coll is maintained as 2, then system will not plan for procurement proposals agains that project. Please check material master setting and change the same to 1 and re-run the MRP.
Thanks & Regards,
Ramagiri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pushkar,
Please check individual/collective indicator in the material master is set to 1 so that all material will get planned in MD51 other wise you need to run MD02 to plan the dependent materials.
Please check WBS element is assign to your planned order there is no need to use Read PP master data.
Also check any exception message there in MD04.
Please refer the below link,
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 13 | |
| 7 | |
| 6 | |
| 5 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.