Hi,

I need to create two operation in parallel but I cannot achieve it.

First of all I create the routing with three operations as show in the image:

Then, I create a new sequence in parallel as shown:

But when I create a production orden, the production times are not the same for both operations.

¿How can i do to create a routing with two operation thar works at same time?

Thanks.

0 Likes

Accepted Solutions (1)

Accepted Solutions (1)

former_member214736
Participant
0 Likes

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello

Pay attention on the value selected for the field "alignment key" on the sequence detail.

If you want to have both operations starting on the same time, you should set the value 1 for this field.

The following link explains this setting in more detail:

Alignment Key in Parallel Sequences - Routings (PP-BD-RTG) - SAP Library

BR