hi,

while releasing the order below error appear please help.

@5D\QWarning@ %00000000001   Work center APAC-L in plant  has no cost center @35\QLong text exists@ Costing

while doing confiration below error appear

ck 282, work center has no cost center.

reg.nsm

0 Likes

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Likes

Hi NS,

In work center costing TAB (APAC-L) you need to maintain cost center. While creation of master data for work center you can assign the cost center for the above work center.

Hope it helps you and doubts please revert me.

Regards,

Madhu.G

Former Member
0 Likes

Hi,

done the same.

now while doing confirmation the error is Document number for general ledger document could not be determined

reg. NSM

Former Member
0 Likes

Hi,

Please consult your FI consultant for the same.

Regards,

Alok Tiwari

Former Member
0 Likes

ok. thanks.

i want to create a order for minimum lot size 500 after MRP run and also the order should create in multiple of 500. please help

Former Member
0 Likes

Dear,

Specify rounding value as 500 in the MRP view. It will generate planner order of 500 if the requirement is below 500 and then in the multiples of 500 if the requirement is more than 500.

Regards,

Nitin Kurhade

Former Member
0 Likes

thanks Nitin.

Answers (2)

Answers (2)

Former Member
0 Likes

Hi,

Check the workcentre APAC-L in tcode CR03. Cost center must be assigned in workcenter costing tab with active validity date.

Regards,

Dharma

Former Member
0 Likes

Hi,

i have checked validity date it is from 01.01.2012 to 31.12.2012

reg. NSM

Former Member
0 Likes

Hi,

validity date 31.12.2012 is expired. Extend the validity date to 31.12.2013.

Regards,

Dharma

Former Member
0 Likes

Hi,

i have changed the date now the error is Document number for general ledger document could not be determined

Former Member
0 Likes

Hi,

Please assign a cost center in the work center APAC-L in the costing tab of it.

Regards,

Alok Tiwari