on ‎2023 Nov 28 7:43 AM
HI Everyone!
I have a raw material with dependent requirements. My planning time fence is 56 days (29.01.2024) I have a schedule agreement for this part number. MRP type: P1
Schedule generated automatically but only outside the PTF ( this is because P1 type if im correct). My main problem is that my stock fall below 0 already today (0 stock and first depreq dated today) however the scedule lines are waiting outside the PTF WITHOUT any exception msg. Is this normal? What should I do to get exception msgs to pull in the deliveries in order to avoid the shortage situation?
Here is a screenshot about the problem. 2023-11-28-083214.png
Thanks in advance!
Request clarification before answering.
Hello
Did you define tolerance values in the rescheduling customizing? If those scheduling lines are within the tolerance values, then MRP will not generate any exception.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 39 | |
| 25 | |
| 21 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.