Hi

Following is my requirement. I want to calculate total Material utilization

For this purpose I need following data

1. Planned qty. for component w/o scrap

2. Oder delivered qty.

3. Process order planned qty.

Let me know from which table-fields I will get these qty??

Thnx

Nilesh

0 Likes

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Likes

Have you tried the reoprt MCBA for usage values? Not sure if that is what is required but may help.

Former Member
0 Likes

HI Nilesh,

Try PLAF for planned qnty and for order dellivery MKPF for 101 movement type

Thanks