cancel
Showing results for 
Search instead for 
Did you mean: 

Material type

08-26-2008 6:10 AM
487 views 5 comments Go to solution
0 Likes
SAP Managed Tags
Subscribe

Dear All,

for a particular material which is already created through material type FERT, can we change the material type to HALB for the same material.if so,then how and what are the points needed to consider for such process?

regards,

indranil

0 Likes

Accepted Solutions (1)

Accepted Solutions (1)

former_member192897
Active Contributor
0 Likes

Please use transaction MMAM / SAPMM03Z in SE38..But first of all you've to check if it is possible to change The material type .

Material type cannot be changed. If :

1.Purchase orders exist .

2.The material is already used in BOM items whose item category defines quantity-based inventory management. However, quantity-based inventory management is not defined by the new material type.

3.Production orders exist for the material. This is not allowed if only external procurement is defined for the new material type, or if the new material type has a different account category reference than the old material type.

4.Stock is already exist for the material

Regards,

Ashok

Edited by: Ashok Kumar Telikula on Aug 26, 2008 9:48 AM

Answers (4)

Answers (4)

Former Member
0 Likes

use split valuation for the mat for 2 diff mat type.

for fert it goes to one account and and other mat type it goes to other gl a/c. Since the master data is same split valuation will be an option.

rewrd

kunal_ingale
Active Contributor
0 Likes

hi

check t code MMAM for the material type change

or MMZ2 for material type and industry sector

for changing the material type the attributes of both the mat type should be same

like val class ,

regards

kunal

Former Member
0 Likes
deiva
Active Contributor
0 Likes

Hai,

You can do the Transaction MMAM - Material type changes but you have to consider the following

the material dosenot conatain any open purchase requisitions, open reservations & open purchase orders. Also material stock should be zero.

Remember the new material type should have same attributes same as old material type.

OLD Material New Material

1) Standard Price 1) Standard Price

2) Manufacture part 2) Manufacture part

profile actvated profile actvated

3) Quantity & Value 3) Quantity & Value

Updation in all areas Updation in all areas

4) should have same GL 4) Should have same GL acs

acs