Material quantity calculation after Batch Determination

09-26-2017 4:45 AM
730 views 2 comments
0 Likes
SAP Managed Tags
Subscribe

Hi Gurus,

I'm facing an issue on material quantity calculation, after batch determination in the process order, as you can see below, the system add a line and my formula get wrong line to proceed the calculation.

Below are the formula I set in the receipe

Someone can help me on this issue?

Thanks!

0 Likes

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Likes

you saw this note?: 674581 - Material quantity calculation after batch determination

Former Member
0 Likes

Hi Jürge,

Thank you for your answer. I applied the note and nothing is change, I still have the same issue. Are there some additional steps I need to proceed before the MQC?