Hi All,
I am trying to create a work centre in t.code CR01. I have entered Plant, work centre and work centre category system throwing error.
Error : Work centre category 0006 does not exist.
I have verified in SPRO, Entry 0006 work centre category is exists.
Please let us know, If any assignments are missing in SPRO.
Best Regards,
Chandrasekhar
Request clarification before answering.
Chandrasekhar,
You need to use transaction CNR1 to create a work center with category 0006, as this category is relevant for Project Systems only.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Chandra,
In OP40-select 0006-then click on Application ,new entries,then include P routing for production as you are trying to create a prodcution work center
Regards,
SVP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In SPRO for Work centre category 0006 ,allow it for task List type routing.After then it will allow to create work centre .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 30 | |
| 14 | |
| 9 | |
| 4 | |
| 4 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.