Hi
I have created P.O without Freight Amount say Rs 5000. Now Supplier has sent Invoice with Rs 5000 + Rs 500 Freight amount. Now how i should create DownPayment Request with Rs 5500. I have 1 validation that DownPayment Request amount should not be greater than P.O Amount.
Thanks
Request clarification before answering.
Hi,
Bypass the TN for time being is the option you can do.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Updating Purchase Order by adding Freight amount.