Hi all, please tell me the difference between VB and VM (MRP type)? Also please send me a relavent document if you have on this.

-Sachin

0 Likes

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Likes

Sachin,

In VB we need to enter Re-order point quantity in the MRP view of the material master, whereas in VM system calculates the Re-Order point itself based on certain definations made.

For more details SAP help is the best place. Here is the link ...<b><a href="http://help.sap.com/saphelp_47x200/helpdata/en/a5/e82be6a27311d3a82e0000e82a3c24/frameset.htm">Re-order Point Planning</a></b> or <a href="http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d256344af11d182b40000e829fbfe/content.htm">Explaination</a>

Regards,

Prasobh

Answers (1)

Answers (1)

Former Member
0 Likes

Hi

In VB, the triggering of planned order is based on the stock. If the stock is less than re-order point. Then only procurement proposal will be raised. Before than no procument proposal even though you have P.I.R ( customer demand ).

Once the procurement proposal is created.

1) Plan order = Max stock level-present stock if the P.I.R quantity is less than this quantity.

2) Plan order = P.I.R - stock .if the P.I .R is more case 1 ) scnario.

In VM

Reorder point will be calculated by 2 methods

method 1 ) Max stock leve - Stock = X

Method 2 ) P.I.R + reorder point-stock = Y.

Plan order will be raised for either X qty or Y qty whic ever is >.

This will try to keep minimum stock of reorder level.

I hope this will be use ful. Please reward points if use ful

Regards

J.S