hello,
any body plese help me how to delete process order once the order was relesed and saved.because i want to create new process order in place of existing order.
hussain
Request clarification before answering.
I think you just release,,,,not issued any components and confirmed...if so
follow the menu path as below in co02
Function delition flag>activate
or
Function -->restrct processing -->lock
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
pl come back
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rashed,
In addition: I'm not sure if you use PI-sheets, but if you already generated the Control Recipe, you will have to cancel the PI-sheet as well.
Trx. CO60, select the appropriate PI-sheet, menuoption PI sheet -> Discard/Cancel.
Good luck, AJ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Rashed,
Mostly PP users will not have the authorisation to set deletion flag, if so in your case you can just set TECO & CLSD status to the order. This can be done in the change mode of the order - COR2.
If any of the above status is set, this order becomes not relevant for MRP and if demand persists after MRP run a new planned order is created.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 13 | |
| 7 | |
| 6 | |
| 5 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.