Hi SAP experts,
I'd appreciate it if you could let me know if someone here had a requirement to join the project data source with the purchase orders and overcome the following warning/error message:
"The Field Baseline Plan Data Details-Base Task of type UUID does not fit to field Purchase Order Account Assignment-Project Task of type ProjectElementID"
I am getting the same message regardless of which project's data source (Baseline Plan Data Details or Project Cost and Revenue - Aggregated) or joins type I am using.
My problem is that I cannot pull out the project's information such as plan or baseline values by project task with the purchase orders on the same data source and report. This is because the values are repeating, and I cannot correct this using any key figures calculation or restriction.
Has someone had a similar requirement or could find out a way to solve it?
I appreciate if you could share your thoughts or any suggestion of how to solve this issue.
Request clarification before answering.
Hi,
I would like to share the solution for further reference. I used the Project Task (MD) and it worked as expected.
Thank you,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 12 | |
| 7 | |
| 6 | |
| 5 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.