Dear Friends,
While doing the CK24 Costing run the following erros are coming.
701 Marking not authorized for period 010 / 2011 in company code 1000
790 *************** Summary Test run: *********************
705 Of 0 materials, 0 cost estimates were updated successfully
Kindly Suugest me at the earliest.
Jyothshna
Hi,
before you can mark a standard cost estimate, you need to set the marking allowance for the company code and period.
This marking allowance has probably not been issued yet. Please check this in txn CK24.
Best regards,
Antje
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
please open your mm periods and fi periods for period 10 and fiscal year 2011 (OMSY AND OB52))
krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.